El Rancho Unified School District

KYA is proud to partner with El Rancho Unified School District to provide modernizations funded through Measure ER, a $200 million bond measure, was put on the ballot to:

  • Modernize and transform El Rancho High School to 21st century educational standards.

  • Upgrade our schools to train students with modern skills for jobs of the future.

  • Repair leaky and aging roofs, remove asbestos and other hazardous materials, upgrade heating and air conditioning and replace outdated plumbing, wiring and sewer systems.

  • Improve school security and safety.   

Rivera Elementary School
Durfee Elementary School
Valencia Academy of the Arts
South Ranchito Dual Language Academy

MPR Modernization Projects:

Rivera Elementary School

MPR Modernization & Shade Construction

Start Date: March 2025

Estimated Completion Date: January 2026

October 2025

This week at Rivera, KYA continues steady progress across multiple project areas. Roofing and insulation of the MPR building are ongoing, with drywall installation set to begin soon. Framing of the new stage is advancing, and restroom work continues with the implementation of CCD No. 2.

Safety remains the top priority, with strict protocols in place to minimize disruptions during the transport of equipment and materials. Coordination across teams ensures an organized and efficient jobsite.

Infrastructure upgrades are also underway and will continue over the coming weeks, as Rivera serves as the lead site for upcoming district-wide improvements. Overall, work remains on schedule, reflecting KYA’s commitment to quality, safety, and careful project management.

September 2025

This month, KYA continues steady progress at Rivera. Roofing and insulation of the MPR building are underway, along with continued framing of the new stage. Restroom work also advances with the implementation of CCD No. 2 to align with updated design standards.

Safety remains the top priority, with strict protocols ensuring minimal disruption during equipment and material transport. Infrastructure work is progressing as Rivera serves as the lead site for upcoming district-wide upgrades. These improvements will enhance performance and reliability across multiple facilities.

Overall, construction remains on schedule, reflecting KYA’s commitment to safety, quality, and collaboration as the project moves toward its next phase of completion.

August 2025

This month at Rivera, key projects are moving forward. Installation of the new roofing membrane over the kitchen is underway, ensuring lasting protection for this essential space. Framing of the new stage has also begun, marking progress toward a modernized performance area. In addition, restroom work continues following the resolution of CCD No. 2, keeping construction on schedule.

Safety remains the highest priority, with strict protocols in place to minimize disruptions during the transport of equipment and materials. At the same time, infrastructure improvements are progressing, positioning Rivera as the lead site for upcoming district-wide upgrades. Together, these efforts highlight KYA’s commitment to safety, quality, and efficiency while building a stronger, more functional campus for the future.

July 2025

Exciting progress continues at Rivera Elementary! The new stage addition has reached a major milestone with a successful concrete pour, and the kitchen roof demolition has transitioned to the installation of a brand-new roofing system. As the lead site for district-wide facility upgrades, Rivera is also seeing steady progress on key infrastructure work. Throughout all phases, KYA is prioritizing student and staff safety with strong protocols in place to ensure a secure and disruption-free environment. Thank you to the Rivera community for your continued support as we work toward a more modern, student-centered campus!

June 2025

Construction continues to progress at Rivera Elementary School, with framing and mechanical ductwork installation underway in the Multi-Purpose Room (MPR). A major focus this month has been preparing for the addition of a new MPR stage. Crews have demolished existing concrete and asphalt, begun excavating footings, and are now placing rebar in preparation for new concrete. These updates will enhance the school’s performance and activity spaces, contributing to a more modern and functional facility. Throughout all phases, safety remains the top priority. Measures are in place to minimize disruptions and ensure secure transportation of equipment and materials.

May 2025

Rivera Elementary reached a major milestone this month with demolition now complete and construction activity accelerating. Crews began framing in the Multi-Purpose Room and removed concrete and asphalt in preparation for a new stage addition. Building upgrades are officially underway as subcontractors arrive onsite. Rivera leads the district schedule, with infrastructure work kicking off ahead of other campuses. As part of broader improvements, these districts are also set to receive a new 40-by-20-foot metal shade shelter, offering a much-needed outdoor space for students and staff. Safety remains a top priority, with careful coordination to minimize disruption during ongoing work.

April 2025

Throughout April, Rivera Elementary was the lead site for construction progress. The month began with focused efforts on abatement and demolition of the old multipurpose room, with KYA taking extensive precautions to minimize disruption to students and staff. By the end of the month, demolition had been completed, marking a major milestone in the project timeline. KYA immediately began preparing for the next phase—initiating building upgrades. Safety remained a top priority, with crews diligently coordinating material and equipment handling to ensure a secure, orderly environment throughout all phases. Rivera served as the launch point for the district’s phased construction approach, setting the pace for work at other campuses.

March 2025

In March, KYA successfully launched early construction activities at Rivera Elementary, prioritizing safety and minimizing disruptions to daily school life. The team began with the installation of temporary facilities and protective fencing to create a secure construction zone. Following these preparations, a specialized abatement and environmental crew initiated work inside the former MPR building. With demolition activities scheduled to begin at the end of the month, KYA continues to manage on-site logistics with precision—carefully coordinating the movement of equipment and materials to avoid distractions for students and staff. The team remains on track and committed to delivering a safe and efficient construction process in close coordination with the District.

February 2025

A new temporary lunch shelter is now in place to support students while the MPR undergoes construction. Safety fencing and designated zones have been established, with full construction scheduled to begin next month.


Durfee Elementary School

MPR Modernization & Shade Construction

Start Date: March 2025

Estimated Completion Date: January 2026

October 2025

At Durfee, KYA continues progress on the MPR with ongoing electrical infrastructure work, drywall installation, and wall closures. These upgrades are essential to completing the space and ensuring long-term functionality.

An experienced environmental team is actively supporting all work to guarantee a safe and compliant process. KYA remains committed to minimizing disruptions while maintaining a secure environment for students, staff, and the school community.

Careful coordination and planning keep the project on schedule, allowing steady advancement across all trades. Overall, work at Durfee reflects KYA’s dedication to safety, quality, and efficiency, ensuring that the MPR improvements are completed smoothly and prepared to support the school’s future needs.

September 2025

This month at Durfee, KYA continues progress on key infrastructure improvements. Work on the roofing membrane is underway, along with ongoing installation of electrical infrastructure for the MPR. These upgrades are essential to supporting long-term facility performance and reliability.

An experienced environmental team is actively involved to ensure all work meets safety and compliance standards. KYA remains focused on maintaining a secure environment for students and staff while minimizing disruptions to daily campus activities.

Although no major new updates are reported this week, preparations and progress continue steadily. The project remains on schedule, reflecting KYA’s commitment to safety, quality, and efficient coordination as Durfee moves closer to the next phase of construction.

August 2025

At Durfee, framing upgrades are scheduled to continue over the next several weeks, marking an important phase in the campus improvement plan. These upgrades are designed to strengthen the building structure, ensuring long-term safety, durability, and functionality for students and staff. Careful planning and phased implementation are helping to maintain steady progress while keeping the project on schedule. Supporting this effort is an experienced environmental team working closely with KYA to ensure that all activities are carried out in a safe and compliant manner. Their oversight plays a critical role in maintaining the highest standards of environmental health and safety, giving added assurance that the work is being completed responsibly.

July 2025

At Durfee Elementary, framing upgrades are in full swing and will continue in the coming weeks. An experienced environmental team is on-site to assist with further investigation into the electrical systems, ensuring everything moves forward safely and in full compliance with regulations. KYA remains committed to keeping the campus safe and minimizing disruptions to daily school life while staying on track with the construction timeline. We appreciate the Durfee community’s cooperation as we continue shaping a better learning environment for all.

June 2025

Demolition and abatement activities are progressing smoothly and remain ahead of schedule. This week, crews also began roof demolition and selective demolition, which will continue into next week. A skilled environmental team is on-site to support these efforts, ensuring all work is performed safely and in compliance with regulations. KYA remains committed to maintaining a secure and disruption-free environment throughout the process. Careful planning and coordination continue to be top priorities, helping to avoid interference with daily school operations and ensuring a smooth workflow. With steady momentum and expert oversight, the project is advancing as planned. The successful start of roof and selective demolition marks a significant step toward the next phase of work.

May 2025

Durfee Elementary is steadily moving through demolition and abatement, marking significant progress on the project timeline. KYA’s crews are actively managing the site with safety at the forefront, ensuring that student and staff routines are not disrupted. Like the other campuses, Durfee is on track to receive a new metal shade shelter, which will offer a flexible and shaded space for outdoor activities. As Rivera’s upgrades continue, Durfee is positioned to enter the infrastructure phase in the coming weeks.

April 2025

April marked the start and steady advancement of demolition and abatement work at Valencia Elementary. Early in the month, while crews awaited clearance from ongoing abatement at Rivera, site inspections and area securing took place. Once work was authorized, Valencia saw full mobilization of KYA crews and environmental specialists. By month’s end, abatement and demolition were nearly complete, with all signs pointing to a smooth transition into the next phase. KYA’s management of site safety and workflow logistics ensured minimal disruption to daily school operations, helping to keep the project firmly on schedule.

March 2025

March was marked by focused preparation at Durfee Elementary, as KYA completed jobsite setup and reinforced safety infrastructure around the future construction zone. The team prioritized establishing secure boundaries and maintaining an organized environment, conducting thorough site inspections in collaboration with subcontractors. While construction is temporarily paused, KYA is aligning efforts with the District to finalize outstanding project elements. Abatement and demolition at Durfee will begin once preceding work at Rivera and South Ranchito is completed, with all safety and scheduling protocols already in place to support a smooth start.

February 2025

KYA completed a temporary lunch shelter at Durfee Elementary to replace the MPR during construction. Safety zoning and fencing has commenced to prioritize the safety of students during construction which will be starting next month.


Valencia Academy of the Arts

MPR Modernization & Shade Construction

Start Date: March 2025

Estimated Completion Date: January 2026

October 2025

At Valencia, KYA continues steady progress on multiple fronts. Work on air conditioning systems and electrical infrastructure improvements is advancing, supporting long-term building performance. Crews have begun drywall installation and are closing up walls in the MPR, while wall insulation continues throughout the space.

The team is carefully managing all material movement to maintain a safe and organized jobsite, minimizing disruptions to the school environment. Coordination among trades ensures efficient workflow as preparations for the next phase of construction move forward.

Overall, work at Valencia remains on schedule, reflecting KYA’s commitment to safety, quality, and careful project management. These efforts are setting the stage for continued progress and successful completion of the MPR improvements.

September 2025

At Valencia, KYA continues steady progress across multiple project areas. Work is advancing on the air conditioning systems and electrical infrastructure improvements, both critical to enhancing the building’s efficiency and long-term performance. In addition, crews have begun installing wall insulation, marking another step toward completing interior systems.

The team remains focused on maintaining a safe and well-organized jobsite, carefully managing all material movement to minimize disruptions and ensure efficient operations. Coordination between trades continues to drive consistent progress as preparations begin for the next phase of construction.

August 2025

At Valencia, KYA is making steady progress as construction moves forward on several key upgrades. Work has begun on the installation of new air conditioning systems, which will provide more reliable comfort and efficiency for the campus once complete. In tandem, the team is advancing electrical infrastructure improvements designed to support both current needs and future modernization efforts. These upgrades will play a vital role in creating a more efficient and adaptable learning environment for students and staff.

A strong focus remains on maintaining a safe and well-organized jobsite throughout the process. The project team is closely managing all material movement to reduce disruptions, ensure safety, and keep daily campus operations running smoothly.

As these essential upgrades take shape, crews are preparing for the next phase of construction with careful planning and coordination. The steady progress being made at Valencia highlights the district’s investment in long-term improvements that will enhance comfort, reliability, and performance across the campus for years to come.

July 2025

Valencia Elementary is buzzing with activity as crews push forward on multiple upgrades. Framing and electrical infrastructure work in the Multi-Purpose Room (MPR) are progressing well, and installation of new air conditioning systems has officially begun! KYA is managing all material movement with care to protect the safety of students, staff, and families. Organization and safety remain the top priorities as the project moves closer to the next exciting phase. Thanks to the Valencia community for your patience and partnership throughout the process!

June 2025

At Valencia Elementary School, demolition has been completed, marking a key milestone in the project. The focus has now shifted to ongoing electrical infrastructure work in the Multi-Purpose Room (MPR), with framing upgrades set to begin this week. These improvements are essential to modernizing the campus and enhancing functionality for students and staff. KYA continues to manage all material movement with care, maintaining a strong commitment to safety and minimizing disruptions to the school community. Clear coordination and safety-focused planning help ensure that construction activities proceed efficiently and responsibly. Progress remains steady as the team moves toward the next phase of development. With demolition behind them and new upgrades underway, the project is advancing on schedule.

May 2025

At Valencia Elementary, demolition and abatement are complete, and the site is transitioning into the infrastructure phase. Electrical work has started inside the Multi-Purpose Room, keeping the project on track and ahead of schedule. KYA continues to manage construction activity with a focus on safety and minimal disruption to school operations. Valencia is also in line to receive one of the district’s new shade shelters, which will create a more functional and comfortable outdoor environment for lunches, learning and school events.

April 2025

April marked the start and steady advancement of demolition and abatement work at Valencia Elementary. Early in the month, while crews awaited clearance from ongoing abatement at Rivera, site inspections and area securing took place. Once work was authorized, Valencia saw full mobilization of KYA crews and environmental specialists. By month’s end, abatement and demolition were nearly complete, with all signs pointing to a smooth transition into the next phase. KYA’s management of site safety and workflow logistics ensured minimal disruption to daily school operations, helping to keep the project firmly on schedule.

March 2025

Throughout March, KYA focused on securing the Valencia Elementary jobsite and preparing for upcoming construction phases. Temporary facilities and safety fencing were put in place early in the month to ensure the site was well-protected. Conducting site inspections and reinforcing safety protocols in anticipation of the next phase. The team continues to work closely with the District to align timelines and ensure a smooth transition into the construction stage once abatement work shifts to Valencia.

February 2025

To accommodate students during MPR renovations, KYA has installed a temporary lunch shelter. The site has been prepped with safety barriers and fencing as the campus gets ready for construction activities in the coming weeks.



South Ranchito Dual Language Academy

MPR Modernization & Shade Construction

Start Date: March 2025

Estimated Completion Date: January 2026

October 2025

At South Ranchito, KYA has completed installation of the new roofing membrane and continues work on air conditioning systems to enhance building performance. Electrical infrastructure improvements are underway, with additional upgrades scheduled to begin once key milestones at Rivera are reached.

The team is also advancing framing work for CCD No. 1, preparing the site for upcoming construction phases. Coordination among trades ensures that work progresses efficiently while maintaining a safe and organized jobsite.

Although major new updates are limited this week, steady progress continues across all areas. Overall, KYA remains on schedule, demonstrating a commitment to safety, quality, and careful project management as South Ranchito moves toward the next phase of infrastructure improvements.

September 2025

At South Ranchito, KYA has completed installation of the new roofing membrane and continues work on air conditioning systems and electrical infrastructure improvements. These upgrades are key to improving building efficiency and overall performance. Preparations are also underway for the next phase of infrastructure enhancements, which are scheduled to begin once progress at Rivera reaches key milestones.

Work remains steady and on schedule. KYA’s team continues to prioritize safety, organization, and minimal disruption to school operations while ensuring all systems are built to meet long-term district needs. Overall, South Ranchito remains well-positioned for continued progress as construction advances in coordination with district-wide facility improvements.

August 2025

At South Ranchito, no major construction updates are being reported this week; however, important preparation work is underway to set the stage for upcoming improvements. The focus remains on infrastructure upgrades that will enhance the long-term functionality and reliability of the campus. These upgrades are scheduled to begin once key milestones are achieved at Rivera, ensuring resources and sequencing are aligned for efficient progress across both sites.

Although visible activity may appear limited at this stage, behind-the-scenes efforts are actively moving forward. The project team is coordinating logistics, planning schedules, and preparing materials so that work can begin smoothly when the time comes. This proactive approach minimizes potential delays, supports safety, and ensures the transition into active construction will be well-organized.

July 2025

While no major construction updates are reported this week at South Ranchito, behind-the-scenes preparations for upcoming infrastructure improvements are actively underway. Work at Rivera will help unlock the next phase of activity here. In the meantime, KYA continues to maintain a clean and organized jobsite, ensuring the campus remains safe for students and staff. We thank the South Ranchito community for your patience as we gear up for exciting changes ahead!

June 2025

Demolition and abatement activities are in full swing and will continue through the week as crews prepare for the next phase of the project. A qualified environmental team is on-site, supporting these efforts to ensure all work is performed safely and in compliance with environmental standards. As demolition and abatement near completion, framing upgrades are scheduled to begin this week. These upgrades mark a key step forward in transforming the site into a modern, functional space that better serves the school community. KYA remains focused on maintaining a safe and disruption-free environment for students, staff, and visitors. Careful planning and coordination are helping to keep the project on track and progressing smoothly. With expert teams on-site and steady momentum, the project is well-positioned for continued success in the weeks ahead.

May 2025

South Ranchito Elementary continues to progress through demolition and abatement at a faster pace than originally anticipated. A qualified environmental team remains onsite to oversee safe and efficient operations while avoiding interruptions to campus activities. As the site nears completion of this phase, it is preparing for infrastructure upgrades to begin shortly after work wraps up at Rivera. A new shade shelter will also be added to the campus, providing essential outdoor coverage and enhancing the overall learning environment.

April 2025

Work at South Ranchito was on hold for most of the month while abatement progressed at the earlier sites. However, planning and preparation were underway behind the scenes throughout April. An experienced environmental team was prepped and ready, and by the final week of the month, demolition and abatement began on-site. KYA implemented a smooth handoff and transition, keeping safety at the forefront. Their proactive measures to minimize school interference allowed construction activity to ramp up quickly, aligning with the district’s accelerated schedule.

March 2025

Throughout March, KYA focused on securing the Valencia Elementary jobsite and preparing for upcoming construction phases. Temporary facilities and safety fencing were put in place early in the month to ensure the site was well-protected. Although major construction activities are currently paused while abatement progresses at Rivera Elementary, KYA teams remain active—conducting site inspections and reinforcing safety protocols in anticipation of the next phase. The team continues to work closely with the District to align timelines and ensure a smooth transition into the construction stage once abatement work shifts to Valencia.

February 2025

KYA completed a temporary lunch shelter at South Ranchito Dual Language Academy to replace the MPR during construction. Safety zoning and fencing has commenced to prioritize the safety of students during construction which will be starting next month.


Previous
Previous

El Rancho High School Modernization Project